本網濟寧訊(xun) 8月29日,新(xin)驛煤礦歷時8小時施工,圓滿完成副井(jing)平(ping)衡尾繩(sheng)更換任(ren)務,為礦井(jing)安全高效運(yun)行(xing)打下堅實基礎。
為確保本次(ci)換(huan)繩(sheng)(sheng)工(gong)(gong)(gong)程順利進行,該礦(kuang)施工(gong)(gong)(gong)前組(zu)織召(zhao)開(kai)工(gong)(gong)(gong)程研討會,從安全(quan)(quan)保障、施工(gong)(gong)(gong)步(bu)驟、人員(yuan)組(zu)織等方(fang)面進行深入(ru)研討,編制安全(quan)(quan)嚴(yan)密(mi)的(de)施工(gong)(gong)(gong)技術措施,抽調28名技術骨干成立4個施工(gong)(gong)(gong)小組(zu),科學(xue)分(fen)配(pei)工(gong)(gong)(gong)作(zuo)(zuo)任務(wu)、全(quan)(quan)面做好換(huan)繩(sheng)(sheng)準備工(gong)(gong)(gong)作(zuo)(zuo)。在施工(gong)(gong)(gong)過程中,該礦(kuang)管(guan)理人員(yuan)全(quan)(quan)程盯靠指揮,嚴(yan)格按照措施要(yao)求(qiu)作(zuo)(zuo)業,使用(yong)舊繩(sheng)(sheng)帶新(xin)繩(sheng)(sheng)的(de)施工(gong)(gong)(gong)工(gong)(gong)(gong)藝,采(cai)用(yong)平行交替作(zuo)(zuo)業方(fang)法(fa)更換(huan)新(xin)繩(sheng)(sheng)。經過全(quan)(quan)體(ti)施工(gong)(gong)(gong)人員(yuan)的(de)團結協作(zuo)(zuo)和不懈努力,換(huan)繩(sheng)(sheng)工(gong)(gong)(gong)作(zuo)(zuo)圓滿完成,再(zai)次(ci)刷新(xin)紀錄(lu)。(姜博)